Saturday 20 July 2013

Frame Delivered 20/7/13

So over the last few days the frame has been delivered, its very exciting seeing blue everywhere.

Wednesday 17 July 2013

Stage One Complete 17/7/13

So happy to say that two weeks after we were scheduled to have slabs we have now been slabbed!!!! I must say the children are over the moon.


The rain just has to stay away until lock up from now on lol.

Tuesday 9 July 2013

Piers, Piers and more piers 9/7/13

Today was the big day... 142 piers were drilled and concreted, thank goodness the rain stayed away.

We have lots of photos that I will upload over the next few days.